ACEP At Work – Pilgrim Hot Springs Geothermal Assessment Weekly Project Update
-Two inch pipe was deployed to run temperature logs through thick mud. The last section failed and ~950’ of pipe was dropped into the well.
-Fortunately, this occurred while most of the drilling crew took an R&R break for the week
-Two inch pipe was retrieved using creative fishing techniques and a suite of flowing temperature logs were collected
-Terrasat completed geophysical logs of hole
-KNOM reporter visited Pilgrim site
-NEXT WEEK: Well PS-13-1 will be reamed to the full 14” diameter beginning next week
To receive daily updates contact Max Frey (mefrey@alaska.edu).
Photo by CPike/ACEP